City of Maitland
FL

Consent Item

Agreement with Burgess & Niple - Lift Station No.10 Force Main Relocation

Information

Department:Public WorksSponsors:
Category:Change Order

Financial Impact

Fiscal Impact: 441.351566300-WW703 Cap. Improvement Lift Station CIP Project No. WW001-351-2016001

Meeting History

Sep 18, 2017 6:30 PM Media City Council Regular Meeting
draft Draft

Authorize the City Manager to sign a Professional Engineering Services agreement with Burgess & Niple, Inc., for the amount of $29,690 for additional study & design of Lift Station No. 10 Force Main Relocation Project located at 600 N. Lake Sybelia.

RESULT:APPROVED [UNANIMOUS]
MOVER:Joy M. Goff-Marcil, Vice Mayor
SECONDER:Bev Reponen, Councilwoman
AYES:Dale McDonald, Joy M. Goff-Marcil, John P. Lowndes, Bev Reponen, Mike Thomas

Discussion